SITE PROGRESS – Commercial Extension Cheltenham
Stanley Partnership Architects visited their Clients Listed Building in Cheltenham, Gloucestershire site and photographed the progress made by the Main Contracter ‘Dove’. The blockwork & engineering brickwork has been completed up to the previously erected steelwork for the main two storey structure. The steel floor sheets have been laid and concrete poured and now the second storey block work continues…next week the Glulam’s go in.

 